Chapter 1 - The collusion continues
A criminal scheme devised by Telstra to minimize their losses was uncovered by the Senate in June 1997 (Refer to Senate page 5169 SENATE official Hansard – Parliament of Australia - (see TIO Evidence File No 3-A) more than two years after most of the arbitrations were concluded.
The statement made by DMR & Lane at point 2.23 in their 30 April 1995 report provided to the arbitrator as their final report has haunted me ever since the conclusion of my arbitration i,e;
“Continued reports of 008 faults up to the present. As the level of disruption to overall CBHC [Cape Bridgewater Holiday Camp] service is not clear, and fault causes have not been diagnosed, a reasonable expectation that these faults would remain ‘open’,” (see Exhibit 45-c -File No/45-A)
Did Lane Telecommunications Pty Lty pressure DMR Group Inc (Canada) not (to diagnose my ongoing Ericsson AXE telephone billing problems) because Lane was already negotiating with Ericsson to sell itself to Ericsson, which it did in 1996? Or did Dr Hughes (the arbitrator) disallow DMR & Lane the extra time they advised him on 30 April 1995? Additional weeks, they advised, were needed to investigate these ongoing billing faults (see below) because Telstra had briefed Dr Hughes that these billing issues were systemic right across Australia, and to have made an official finding on my claims left the door open for other similar claims.
In my telephone conversation with Dr Hughes on 4 May 1995, and in my faxe of 5 May 1995, I asked why DMR & Lane had not investigated these ongoing billing faults in their final 30 April 1995 report. As shown in Dr. Hughes's 5 May 1995 letter (See Arbitrator False Evidence File 1), he refused to discuss these ongoing billing issues or allow me to submit evidence these billing issues were still affecting my business (refer also to Chapter 1 - The collusion continues.)
Government corruption is a criminal scheme devised by Telstra to minimize their losses was uncovered by the Senate in June 1997 more than two years after most of the arbitrations were concluded.
Forces at Work - see below
Corruption and Misleading and Deceptive Conduct
There are discrepancies between the arbitrator’s version and my version of Lane's prepared technical consultant report titled Resource Unit Technical Evaluation Report. Mr Alan Smith. CBHC. 30 April 1995. The second paragraph on page one consists of only one short sentence, “It is complete and final as it is,” (see Arbitrator File No/27). However, the second paragraph on the equivalent page (page two) of the arbitrator’s report, also dated 30 April 1995, says:
“There is, however, an addendum which we may find it necessary to add during the next few weeks on billing, i.e. possible discrepancies in Smith’s Telecom bills.” (See Arbitrator File No/28)
There is more information in the arbitrator’s version than mine. The reference to my ongoing billing problems states extra weeks are required to complete the investigation. The arbitrator did NOT provide the extra weeks.
My page two of this report (see Open Letter File No/47-A to 47-D) shows no mention of my billing claim document in my version. However, page three in the arbitrator’s version notes:
“One issue in the Cape Bridgewater case remains open, and we shall attempt to resolve it in the next few weeks, namely Mr Smith’s complaints about billing problems.
“Otherwise, the Technician Report on Cape Bridgewater is complete.” (See Open Letter File No/47-A to 47-D)
How can two identical technical reports with the same 23 technical assessments, both dated 30 April 1995 and apparently both prepared by the same consultants, have one version noting that the “… case remains open, and we shall attempt to resolve it in the next few weeks”, while the other has no mention of it still being open and needing weeks to complete?
Both technical reports state: “A comprehensive log of Mr Smith’s complaints does not appear to exist.” It did exist along with 76 letters which AUSTEL acknowledges did exist from could have been clients, all separate testaments including the Cape Bridgewater BCI and SVT reports exposing how degraded the Ericsson AXE telephone equipment was. The same Ericsson AXE ongoing telephone problems continued for years after the completion of my arbitration. Had this comprehensive log of fault complaints been provided to the technical consultants to assess, they would have had to overrule the arbitrator’s decision not to allow them the extra weeks they had requested to investigate my ongoing billing faults.
Hear again is Government corruption becoming a criminal scheme devised by Telstra to minimize their losses was uncovered by the Senate in June 1997 more than two years after most of the arbitrations were concluded.
A comprehensive log of Mr Smith’s complaints does not appear to exist.
Corruption in Arbitration
To be clear so that the reader understands, a dated chronology of my 008/1800 billing issues were submitted to the arbitrator as a chronology of events. Why didn't the arbitrator look for it or call for a second copy when I provided evidence that my claim advisers had sent it. Were these 008/800 claim documents lost in Telstra's fax screening process on route to Dr Hughes office or did they arive at that office and were diverted to the Sydney office where that office failed to send the infromation back? (see Burying The Evidence File 13-H below)
The arbitrator and his arbitration resource unit failed to value the negative effects that some of these newspaper articles were having on the well-being of my business, particularly when they were combined with various damaging comments from customers, such as: “… the faulty phones had endangered lives and the hospital would not return to the camp unless the phone service could be guaranteed”.
I need to take the reader forward fourteen years to the following letter dated 30 July 2009. According to this letter dated 30 July 2009, from Graham Schorer (COT spokesperson) and ex-client of the arbitrator Dr Hughes (see Chapter 3 - Conflict of Interest) wrote to Paul Crowley CEO Institute of Arbitrators Mediators Australia (IAMA), attaching a statutory declaration (see ”Burying The Evidence File 13-H and a copy of a previous letter dated 4 August 1998 from Mr Schorer to me, detailing a phone conversation Mr Schorer had with the arbitrator early in 1994 regarding lost Telstra COT related faxes. During that conversation, the arbitrator explained, in some detail that:
“Hunt & Hunt [The company’s] Australian Head Office of was located in Sydney and [the company] is a member of an international association of law firms. Due to overseas time zone differences, at close of business, [the company’s] Melbourne’s incoming facsimiles are night switched to automatically divert to Hunt & Hunt Sydney office where someone is always on duty. There are occasions on the opening of the Melbourne office, the person responsible for cancelling the night switching of incoming faxes from the Melbourne office to the Sydney Office, has failed to cancel the automatic diversion of incoming facsimiles.”Burying The Evidence File 13-H.
The fact that Dr Hughes did not official diclose these faxing problems between his Sydney and Melbourne office prior to is hinging on criminal negligence. Dr Hughes also did not acknowledge what happened to the comprehensive log of my phone complaints.
I reiterate, a comprehensive log of my phone complaints did exist.
It is important to note before AUSTEL commenced their investigation into my phone/fax complaints, I provided them with a comprehensive log of my phone complaints which I later supplied an updated copy to Dr Hughes (the arbitrator) to my claim on 15 June 1994 as my interim to my arbitration submission (see File - 7 to 9-A - AS-CAV Exhibit 1 to 47 and File 108 - AS-CAV Exhibit 92 to 127). The nominated documents in those two files AS-CAV Exhibit 1 to 47 and AS-CAV Exhibit 92 to 127 show a comprehensive log of my phone complaints did exist.
Why would I submit an arbitration claim without a comprehensive supporting log of my phone complaints? It is clear from AUSTEL’s Adverse Findings, at points 1, 212, that the government prepared report testimonials supplied by me. Why would I provide the government File - 7 to 9-A - AS-CAV Exhibit 1 to 47 and File 108 - AS-CAV Exhibit 92 to 127 and not the arbitration process?
In the arbitrator's award, there is no mention that the claimant [me] continually raised faxing problems with his office and the TIO office right through the arbitration process. There is no mention in the arbirators award that I refuted both the Cape Bridgewater BCI and SVT testing process. Had the arbitrator received either the BCI or SVT Cape Bridgewater reports which I prepared for his assessment using some of the same material to which the more updated two reports were derived from (see Telstra's Falsified SVT Report and Telstra's Falsified BCI Report) the arbitrator was duty bound under the arbitration agreement to make a finding either way on those reports.
That award does not refer to the AFP investigating these lost arbitration related faxes or that he advised the AFP of the internal faxing problems his Melbourne and Sydney offices were experiencing.
My award was brought down on 11 May 1995. The very next day, the arbitrator wrote to the TIO and discussed one of the deficiencies in the agreement; the insufficient time frame allowed in the arbitration agreement for the “preparation of technical reports” (see Chapter Five below) I had raised this very same issue with the arbitrator the previous week when I requested he give me more time to investigate the disappearance of my comprehensive log of complaints.
Why should my arbitration claim be penalized because of the inadequate handling of the arbitration material once it reached the arbitrator’s office?
As Chapter five shows below, a little more than two hours after Warwick Smith received Dr Hughes’ 12 May 1995 letter, he put out a media release stating:
“The Administrator noted that the arbitration process, under the direction of the independent Arbitrator Dr Gordon Hughes, appointed with the agreement of the parties, had been run in accordance with principals of natural justice.” (See Open Letter File No 55-B)
Warwick Smith both misled and deceived the public in this media release headed 1st Telecom COT Case Arbitration Finalised: even though this release didn’t name which claimant he was referring to, it is well known I was the first to go through the process.
Eight damning letters
Letter One
The first of these eight damning letters was from John Rundell, the Arbitration Project Manager, on 18 April 1995, advised the TIO, the arbitrator and the TIO counsel that:“Any technical report prepared in draft by Lanes will be signed off and appear on the letter of DMR Inc.” ”
“It is unfortunate that there have been forces at work collectively beyond our reasonable control that have delayed us in undertaking our work.
“Any technical report prepared in draft by Lanes will be signed off and appear on the letter of DMR Inc.” (see Prologue Evidence File No 22-A)
The four COT claimants Ann Garms, Maureen Gillan, Graham Schorer and (me) were never told about any of these so-called “forces at work” and nor were we ever warned that, under the nose of the TIO, the TIO’s legal advisor and the Arbitrator, these un-named “forces at work” were allowed to infiltrate and manipulate the arbitration process wherever and whenever they desired, but always with the aim of helping Telstra to defeat the COT claimants.
When these three legal experts, (i.e. Dr Gordon Hughes, Warwick Smith and Peter Bartlett) allowed this very important letter of 18 April 1995 to be hidden from the four COT cases, those so-called ‘legal experts’ directly assisted those “forces at work” to carry out their intended disruption of all four of the COT cases’ arbitrations. If John Rundell had sent a copy of his letter to the four COT cases, as he should have, all four of us could have approached the Federal Government at once because, with Mr Rundell’s letter as evidence, we would certainly have had a very reasonable chance of being granted the rights to have all four processes reviewed and amended, at the very least. And don’t forget, it was the Federal Government who had originally endorsed those first four Fast Track Arbitration Procedures.
Also in this18 April 1995 letter, the arbitration project manager John Rundell (FHCA) was so openly deceptive he wrote to the first administrator of my arbitration TIO Warwick Smith, copying the same to arbitrator Dr Hughes, stating, “Any technical report prepared in draft by Lanes will be signed off and appear on the letter of DMR Inc.” (See Prologue Evidence File No 22-A)
On 26 September 1997, John Pinnock, the second TIO to be appointed to oversee the COT arbitrations as they dragged on, alerted a Senate Estimates Committee (see Prologue Evidence File No 22-D) that:
“… Firstly, and perhaps most significantly, the arbitrator had no control over that process because it was a process conducted entirely outside of the ambit of the arbitration procedures”.
This information definitely strengthens our claim that, if the COT cases had been provided with copies of John Rundell’s 18 April 1995 letter, and if we had then also been warned that our arbitrations were being conducted entirely outside of the ambit of the arbitration procedures, and if we had also been told that that meant that Dr Hughes had no control over the process, we would have had enough information to convince the endorser of our arbitrations (i.e. the Federal Government) to have the entire process immediately abandoned and a new, more reliable process designed.
We also need to remember that the arbitration process was administered under the auspices of the Supreme Court of Victoria and that leads us to wonder now, how appalled the members of the Supreme Court might have been if only they had known about the appalling behaviour of Dr Hughes and Warwick Smith, both throughout our arbitrations but particularly when:
- Dr Hughes and Mr Smith decided to allow Telstra to freely manipulate the process, with no oversight in place to stop them; and
- These secretive “forces at work” and how they infiltrated the process to benefit themselves to the detriment of the claimants.
These, of course, were those same un-named “forces at work” who had not only threatened me because I assisted the Australian Federal Police with their investigations into Telstra (see Prologue Evidence File No 22-A), but had also carried out those threats.
In the end, however, even though the Senate was informed of this manipulation of a legal process, still nothing was ever done to support the COT cases in any way. We can’t help but wonder, if this information had been made available to the Federal Government (who endorsed the arbitration process in the first place) would it have been enough to convince them to order the arbitrations to be abandoned and a better, more secure and fairer process put in place.
The Second Damning Letter
John Rundell admitted he knowingly submitted this incomplete financial report into my arbitration process, not runs two arbitration centres, one in Collins Street Melbourne to other In Tsim Sha Tsui, Kowloon, Hong Kong. I wonder how many other arbitrations he has been involved in where known incomplete reports have been used to the detriment of the other party?
Corruption in Arbitration
My arbitration billing issues were raised on the 15th of June 1994 in my Letter of Claim. Open letter File Nos/46-A to 46-J exhibits also show I raised the 008 billing issues on 27 May 1994.
John Rundell, in this 15 November 1995 letter (see Open letter File No/45-A), states:
“As no further progress was likely to be made on these matters, the formal version of the Technical Evaluation Report did not leave the billing issues open.”
In this 15 November 1995 letter, Mr Rundell mentions nothing about my claims of ongoing 008/1800 false recorded message faults telling the callers to my business I am no longer in business. How could a truly independent arbitration resource unit not investigate the worse possible fault being experienced by my business?
Yet the formal DMR and Lane Report, at point 2.23, notes:
“Continued reports of 008 faults up to the present. As the level of disruption to overall CBHC [Cape Bridgewater Holiday Camp] service is not clear, and fault causes have not been diagnosed, a reasonable expectation is that these faults would remain ‘open’.”
This report proves beyond all doubt these ongoing unaddressed billing faults were left ‘open’. At no time did DMR & Lane run a series of tests calls so that they could hear the RVA recorded message when dialling my 1800 number “The number you are calling is not connected.”
Open Letter File No/47-D is page 40 from the final version of the report I received during my arbitration – it includes 14 more sets of claim documents than what is on the list contained in Open Letter File No/47-C.
The issue of these unaddressed 008/1800 billing problems was a central and major factor of my arbitration claim and so these problems are raised throughout absentjustice.com. This 008/1800 free-call service fault, which so seriously affected the viability of my business, was actually threefold. Firstly, Telstra routed the 008/1800 service through my 005 267267 main, incoming service line, despite Telstra knowing that line was prone to serious problems going back for many years. In fact, the AUSTEL draft findings, which resulted from their investigations into my complaints (see Open Letter File No/4 File No/5 File No/6 File No/7), show AUSTEL condemned the entire phone system that Telstra supplied to my premises. Secondly, both my 055 267267 service and the 008/1800 free-call service were affected by incoming calls failing to connect: telling the caller, “The number you are calling is not connected.”, as well as the same service line locking-up after each terminated call.
Both AUSTEL’s records, and Telstra’s, show that this RVA message suggests the business is no longer operating, a terrible situation for any telephone-dependent business-owner to have to endure. I experienced these multiple 008/1800 RVA telephone faults throughout my arbitration, and for years after, because as shown above, the arbitrator handed down his findings prematurely, despite his own technical consultants warning him that because of the: “… fault causes have not been diagnosed, a reasonable expectation is that these faults would remain “open”. For callers to still be advised that my business was no longer operating when it definitely was operating, and for that message and the locking up of this service line to haunt my telephone line for years after my arbitration, was a deplorable situation for anyone to have been left in and obviously raises the question of what the arbitrations were meant to do if it was not to investigate all the phone problems that brought the claimants into the process in the first place?
On page one of Mr Rundell’s letter, dated 15 November 1995, he also advised Mr Pinnock Open letter File No/45-A that:
“Discussions were held with Telecom (Mr Peter Gamble) in Mr Smith’s presence during the visit to Cape Bridgewater in April 1995 which provided the following information.
“A second matter involved 008 calls. Again, this matter was current at a late stage (April 1995) of the Arbitration process”.
Mr Rundell’s statements, in the four bullet points on page two of his letter (see File No/45-A), alleges that during this site visit Peter Gamble and I discussed issues concerning the 008/1800 faults and that I and Lanes (the arbitration technical consultants) agreed with Peter Gambles many explanations concerning the 008/1800 issues I had raised in my claim. These statements to Mr Pinnock are a total fabrication and they suggest Mr Gamble’s assertions, that there was nothing wrong with Telstra’s 008 service, were correct and my arbitration claims, concerning a deficiency in the 008 service, were a figment of my imagination.
If Mr Rundell had told the truth, in his 15 November 1995 letter to Mr Pinnock, he would have admitted my claims were true and acknowledged that I had first raised the ongoing telephone billing problems as a major issue, affecting the viability of my business, in my 27 January 1994 Fast Track Settlement Proposal (FTSP) interim letter of claim. This claim was jointly addressed to Warwick Smith (the first TIO), Dr Hughes (then the assessor) Peter Bartlett (the TIO’s counsel) and Mr Rundell. A 37-page chronology of evidential material, Arbitration Reference Number-P-1289, attached to my submission, was proof enough that my business was experiencing a major telecommunications problem that needed a full investigation. Warwick Smith, however, advised me to sign for the arbitration process because, he assured me, the ongoing billing issues would be addressed as part of that process.
My arbitration letter of claim, dated 7 June 1994 and provided to the arbitrator on 15 June 1994, also referred to my 27 January 1994 settlement letter of claim and Arbitration Reference Number-P-1289. Furthermore, the final versions of the DMR and Lane (arbitration technical consultants) 30 April 1995 report twice directed the arbitrator’s attention to the fact that my complaints were still ongoing and still being reported, right up to the date of their reports. They also advised Dr Hughes, in writing on 30 April 1995, that they had not investigated this part of my claim and required extra weeks to do so.
Corruption in Arbitration
As AUSTEL (now ACMA) and Telstra each wrote to Dr Hughes on three separate occasions, in December 1994. Each of those letters discusses these major ongoing billing issues. AUSTEL’s letter, dated 8 December 1994, to Dr Hughes Open letter File No/46-I even states:
“A major consideration in AUSTEL’s pursuit of the issues raised by Mr Smith was the likelihood that these problems, if proved to exist, would almost certainly affect a number of other Telecom customers.”
It has since been confirmed from Call For Justice Evidence File 12 that AUSTEL first raised these 008/1800 complaints, on my behalf, with Telstra in June 1993 and wrote to Telstra again concerning my claims, on 6 January and 27 January 1994, during my FTSP. Between the 4 October 1994 and 16 December 1994 (see Open letter File No/46-F to 46-J) AUSTEL and Telstra were writing about these 008/1800 arbitration billing claim documents. In March 1994, Telstra’s CEO, Frank Blount and I discussed the same ongoing billing problems and he advised he would do everything he could to rectify these problems as well as my complaints of network congestion between Warrnambool and Portland. In mid-1999, after retiring as Telstra’s CEO, Frank Blount published Managing in Australia, which acknowledgement this 1800 billing fault as a major Telstra network software problem Home Page Part Two Evidence File No/10: my unaddressed arbitration claims are still valid.
All three of my individual service lines would lock up at different times after a terminated call. This lock-up problem not only stopped calls and faxes leaving or coming into my business but, on the 008/1800 line, I was charged for the time the line was open even though the call had terminated as the lock-up fault held the line open. When John Rundell, Arbitration Project Manager advised the TIO (see above) that my billing problems were not investigated, he was acknowledging that the lock-up problems on my service lines were also not investigated. In simple terms, by not addressing my billing faults the arbitration process was also not addressing any of my complaints of ONGOING PROBLEMS.
If Mr Rundell had told the truth to Mr Pinnock and explained the real reasons why NONE of those ongoing billing problems was investigated or addressed during my arbitration, then my claims would have been investigated back then, in November 1995. Mr Pinnock wrote to me twice in August 1995, as the administrator of my arbitration, stating that he was obliged to investigate my complaints of such skullduggery. The untruths Mr Rundell concocted in that 15 November 1995 letter immediately brought that investigation to a complete halt.
Did the arbitration resource unit understand that when they failed to investigate the ongoing billing problems, they did not address the cause of the billing issues? The billing issues included calls registering into the holiday camp lines through Telstra’s Call Analyses Charges System (CCAS) that I was charged for, although the connection actually failed, and a fault where successful calls were terminated but the line remained engaged, thus prohibiting incoming or outgoing calls. The failure of the engaged line to correct itself, leaving the line effectively frozen, was significant.
This fault was only obvious when dialling out from the business office. From 1993 onwards, Telstra often advised us to disconnect the phone at the wall socket and then plug it back in to free up the line. This indicates the fault was in either the phone or the actual phone line. In order to dial out of the office when this particular fault was present (it was intermittent), we had to disconnect the line at the wall after every call.
When it was revealed the arbitrator refused his technical consultants the extra weeks they required to assess all of my claims – and thus only 11 per cent of my claim documents were investigated – the government communications regulator demanded Telstra address these arbitration issues (see Open letter File No/46-A to 46-l).
This 3 October 1995 letter from AUSTEL to Telstra’s arbitration defence liaison officer and copied to the TIO was written after I had explained to AUSTEL the Ericsson AXE lockup faults were also affecting the billing of all of Telstra customers who were connected to an AXE exchange and therefore this unaddressed AXE fault was a two-fold fault. This letter to Telstra, states:
“I write concerning charging discrepancies raised in 1994 by Mr Alan Smith of Cape Bridgewater Holiday Camp regarding his 008 service, and the wider issue these discrepancies raise for Telstra’s 008/1800 customers. These matters have been the subject of previous letters from AUSTEL to you and to [Telstra], dated 4 October 1994 and 1 December 1994, respectively. The charging discrepancies have again been raised with AUSTEL by Mr Smith following the conclusion of his Fast Track Arbitration Procedure.” (See exhibit 46-K / Open letter File No/46-A to 46-l).
On 14 October 1995, AUSTEL’s Darren Kearney wrote to me under the subject heading Charging Discrepancies Related to Telstra’s 008/1800 Service:
“As noted in my letter to you of 4 October 1995, AUSTEL has written to Telstra regarding the issues originally raised by you in 1994. The letter refers specifically to charging discrepancies raised in 1994 by Mr Alan Smith of Cape Bridgewater Holiday camp regarding his 008 service. …
“As previously advised, you will be informed of the outcome of this matter.”
Unbeknown to me, on 16 October 1995, five months after my arbitration was concluded, and hence outside the arena of the arbitration process, the government regulator covertly allowed Telstra to address the worst of the remaining 89 per cent of unaddressed Ericsson AXE telephone exchange faults which I originally submitted in my 15 June 1994 letter of claim (see (See exhibit 46-L / Open letter File No/46-A to 46-l).
When the government regulator allowed Telstra (the defendants) to address civil arbitration issues outside of my arbitration, which prohibited me from legally challenging Telstra (as part of the original arbitration process), the government breached their statutory duty of care towards me as an Australian citizen.
Telstra’s previous CEO Frank Blount acknowledged, publicly in a manuscript published jointly with Bob Joss and titled Managing in Australia, that Telstra suffered from systemic faults. However, we did not acknowledge that when the government communications regulator AUSTEL (now ACMA) allowed Telstra to address some of my 1800 billing faults, outside of the arbitration arena on 16 October 1995, they denied me natural justice, because:
- By allowing only Telstra to comment on my 008/1800 arbitration billing faults, and not me (the claimant), AUSTEL acted as the arbitrator: AUSTEL accepted Telstra’s version of events concerning my ongoing 1800 billing faults. This one-sided process allowed only the defendant Telstra to address my claims, even though the arbitration agreement, facilitated by AUSTEL and endorsed by the relevant Communications Minister Michael Lee, stated I had a right of reply to Telstra’s arbitration defence of my claims.
- Had Telstra addressed these 1800 billing issues in its defence of my claims, during my arbitration from 21 April 1994 to 11 May 1995, Dr Hughes (the arbitrator) would have been able to make a finding either for or against my claims. This would have allowed me my legal right to appeal this part of my arbitration claim if I thought Dr Hughes had erred on a point of law concerning these matters.
- Had Telstra addressed these 1800 billing issues in its defence of my claims and Dr Hughes had found against me, I could have legally challenged Dr Hughes’ award (findings), in 1999, when Frank Blount admitted publicly that Telstra did indeed have a billing problem (during the period I raised these matters). From May 1995 (the end of my arbitration) to Mr Blount’s publication in 1999 is only 4 years and within the Statute of Limitation six-year period for me to submit an appeal. Most people would conclude I would have won my appeal, had Dr Hughes addressed these issues either for or against me, because how could an appeal judge argue against the findings of Telstra’s previous CEO Frank Blount (i.e., his public admission that Telstra indeed had 1800 billing problems.
I again ask, why did John Rundell become involved in this 1800 deception? The statements concerning the 008/1800 problems raised by Mr Rundell in his letter of 15 November 1995 (see above), do not coincide with the statements made by Frank Blount, in his publication in Managing in Australia.
Just as worse, another Alan Smith who used to live in Discovery Bay, on the other of Cape Bridgewater like me before and leading up to my arbitration, had been battling Telstra over many months receiving legal letters from a leading Victoria (Warrnambool law firm) acting for a financial debt collector issuing summons (two I still have) for non-paid Telstra accounts. Freehills Hollingdale & Page fax identification stamp is visible on these documents. This is the same Alan Smith who later informed me of regularly receiving my arbitration-related documents from Telstra. Had Dr Hughes investigated my claims of lost faxes and road mail deliveries, that investigation might well have uncovered Telstra's arbitration defence unit Freehills mistakenly sent some of my arbitration material to this Alan Smith. I use the word mistakenly because I have no proof it was a deliberate part of Telstra's COT Cases strategy to 'stop me at all costs' from proving my claim.
This download link Prologue Evidence File No/6 008/1800 billing issues … – Absent Justice confirms Telstra’s previous CEO Frank Blount’s acknowledgement, in Managing in Australia (1999), that Telstra had a major 1800-free-call billing software problem: the same problem Dr Gordon Hughes, the arbitrator of my case, disallowed his technical consultants the extra weeks they advised was needed to investigate these ongoing problems. Had Dr Hughes allowed his arbitration unit the extra weeks their draft findings stated they needed to investigate my 008/1800 claims (see also Open letter File No/46-A to 46-l), they would have also uncovered that the 1800 service to my business was trunked through the 055 267267 service line. When Dr Hughes stopped DMR and Lane, his technical consultants, from investigating my 008/1800 arbitration claims, did he realise he was also stopping DMR and Lane from investigating my 055 267267 services? This line was still fault-ridden – and remained that way for a further nine years after my arbitration was supposed to have fixed these faults. (See Burying The Evidence File 10-A to 10-C).
Although Telstra successfully suppressed the evidence of these widespread faults in its service during the COT arbitrations, surely, once Mr Blount admitted these faults, publicly in 1999, Telstra’s board of management should have immediately reopened that part of my arbitration claim and awarded me damages. Telstra has, to date, ignored Frank Blount’s admissions.
Combine this letter of 15 November 1995 with the second and third named letters discussed above and below and it becomes obvious that John Rundell, should have been questioned more than twenty years ago concerning his questionable conduct both during and after my arbitration.
It is also clear from Front Page Part One File No/1, that on this occasion on 23 May 1994 six documents faxed from my office to the arbitrator's office did not reach their intended destination. I alerted the arbitrator and actually met with Warwick Smith to discusses these lost faxed arbitration claim documents. I was not given permission to re-send these faxed documents to the arbitrator for reassessment.
Many within the Establishment said that it was actually unconstitutional to force the COT cases into an arbitration process with Telstra while the Australian Federal Police (AFP) were still investigating Telstra for alleged phone and fax hacking of the COT cases’ businesses and, furthermore, it was acknowledged that it was clearly an unworkable process. This didn’t stop the arbitrations, however, although it does raise a number of important questions:
- How could two separate investigations into Telstra, for allegedly unlawful conduct, be undertaken by two different organisations at the same time, i.e., an arbitrator as well as the AFP? As far as we can find, this situation is unheard of in any other Western democracy.
- While all the COT cases attempted to keep their individual small businesses going while their arbitrations continued, how could we be expected to submit complex submissions to an arbitrator and, at the same time, assist the AFP with their investigations?
- Why were we COT Cases not allowed to resubmit lost faxed claim documents which we could prove did leave our various offices?
- Who decided that this situation would be allowed to continue?
I beleive it is appropriate that we revisit the above deceptive statements made by John Rundell above, because had all of my submitted billing claim documents been investigated by the arbitration process instead of in secret with Telstra and AUSTEL on 16 October 1995, these past twenty-five years would have been somewhat fifferent.
If you read Chapter 3 - The Sixth Damning Letter below, you will understand why the Arbitration Project Manager mentioned should not be operating an arbitration centre in Melbourne and Hong Kong in 2022.
The following link is from John Rundell’s own website – https://www.johnrundell.com › Arbitration – in which he promotes: “As Technical Expert to 6 major Arbitrations known as the ‘Casualties of Telecom’ Cases, one of Australia’s most protracted and complex arbitration processes.”
However, Mr Rundell fails to mention that his letter to the arbitrator, administrator and legal counsel Open letter File No/45-A discusses how he intended to transfer Lane Telecommunications’ technical findings onto the letterhead of DMR (who was flown out from Canada to assess my arbitration claim) to imply that Paul Howell of Canada had prepared the report. Evidence on my website absentjustice.com shows Lane did all the assessment before being purchased by Ericsson of Sweden.
Likewise, there is nothing on his website stating he told Mr Pinnock (the second appointed administrator to my arbitration) on 15 November 1995 that: “As no further progress was likely to be made on these matters, the formal version of the Technical Evaluation Report did not leave the billing issues open.” (See File 45-A Open letter File No/45-A) Chapter 1 - The collusion continues shows they were left “open”
In fact, when Paul Howell from Canada learned what was taking place he wrote in the formal DMR and Lane Report, at point 2.23, that:
“Continued reports of 008 faults up to the present. As the level of disruption to overall CBHC [Cape Bridgewater Holiday Camp] service is not clear, and fault causes have not been diagnosed, a reasonable expectation is that these faults would remain ‘open’.
This type of government corruption and their criminal scheme devised by Telstra and its lawyers to minimize its losses to the detriment of those it had bastardized before and during the COT government-endorsed arbitration process would have been an unbelievable story to most reading this website had it not been for the evidence that can be downloaded from this it which proves my claims.
Next Page ⟶